7 min read By Local Nest Group, Hampshire Updated June 2026

A loft conversion takes 6–18 weeks on site depending on type — and most people are surprised the building work is the quick part, because the full journey from first enquiry to a finished, signed-off room is usually 4–7 months once you include design and planning. This guide breaks down the timeline stage by stage so you know what to expect.

Build time by type

TypeTime on site
Velux / roof light6–8 weeks
Dormer8–12 weeks
Hip-to-gable10–14 weeks
Mansard12–18 weeks

These are build times only. The full project is longer once you add the design and planning stages before work starts.

The full timeline, stage by stage

Here's the typical journey for a dormer conversion:

All told, expect roughly 4–6 months end to end for a typical dormer, longer where full planning is needed.

What makes it faster or slower

Can you live there during the work?

Usually yes — most of the work is up in the roof, above your living space. There's noise and some disruption, especially during the staircase installation when the loft is opened up to the floor below, but the work area is sealed off and kept clean. See loft conversions for our full process.

Get an exact price or timeline for your project

Book a free survey and we'll give you a fixed-price quote and a realistic programme — across all of Hampshire.