A single storey extension takes 10–14 weeks on site, and a double storey 16–20 weeks — but the full journey from first enquiry to a finished, signed-off room is usually 5–8 months once design and planning are included. Here's the honest stage-by-stage timeline, what makes it faster or slower, and what living through it is really like.
Build time by extension type
| Type | Time on site |
|---|---|
| Side return | 10–12 weeks |
| Single storey rear | 10–14 weeks |
| Wraparound | 14–18 weeks |
| Double storey | 16–20 weeks |
These are build times. Add the design and approval stages below for the full picture.
The full timeline, stage by stage
- Weeks 1–3 — Survey & design. Free survey, measured drawings, design development until you're happy.
- Weeks 3–11 — Planning or PD. Many rear extensions are Permitted Development (faster); full applications take about 8 weeks for a decision. Conservation Areas more often need applications.
- Weeks 8–13 — Structural design & building control. Calculations, technical drawings, building regs submission. Runs partly in parallel with planning.
- Weeks 12–15 — Fixed price, party wall & scheduling. Contract signed; party wall notices served where excavation is near a neighbour.
- Then 10–20 weeks on site. Groundworks and foundations (weeks 1–3), structure and roof (4–8), glazing and watertight (8–10), first fix, plaster, second fix and finishes (10–14+), knock-through to the existing house usually late to keep you sealed off from the works.
Total: roughly 5–6 months for a PD single storey, 6–8 months where full planning applies or for double storey projects.
What makes it faster or slower
- Permitted Development saves the ~8-week planning wait — the single biggest factor.
- Groundworks surprises — drains, tree roots and poor soil are the most common site delays; a thorough survey minimises them.
- Weather — foundations and roofing are weather-sensitive; winter starts carry a little more risk.
- Glazing lead times — bespoke bifolds and roof lanterns can take 6–10 weeks to manufacture; we order early so they never hold the site.
- Decisions — kitchens, tiles and finishes chosen early keep the programme intact.
Can you live at home during an extension?
Almost always, yes. Unlike a refurbishment, an extension is built outside your existing walls — the site is sealed off, and the disruptive knock-through into your kitchen usually happens in the final weeks. Expect noise, some dust and a garden that's a building site for a few months; expect to keep cooking in your kitchen for most of it. For a kitchen extension we plan the switchover carefully so you're without a kitchen for days, not weeks.